UZBEKISTAN NATURAL GAS POWER PLANT

UZBEKISTAN / KHOREZM

OVERVIEW

With the Uzbekistan natural gas combined cycle power plant with a total installed capacity of 174 MWe, we make a significant contribution to energy supply and meet the energy needs of approximately 500,000 households with the energy we produce.

In March 2021, we signed an agreement with the government of Uzbekistan for the construction of a natural gas combined cycle power plant with a total installed capacity of 174 MWe in Khorezm City, Uzbekistan and the sale of the electricity generated from the plant to National Electric Grid of Uzbekistan-NEGU. The electricity generated at this power plant is directly connected to the country's national electricity transmission grid and is used to meet the country's demand for electricity.


Source

Natural Gas Power Plant

Installed Power

174 MW

Employees

99

1.2M MWh

ENERGY PRODUCTION PER YEAR

%49

EFFICIENCY

500K

WE MEET THE ENERGY
NEEDS OF HOUSEHOLDS
March 2021Power Purchase Agreement Signage
September 2021Beginning of Construction
March 2022First Production
July 2022%75 Capacity
April 2024%100 Capacity
  • The largest power plant in the state of Khorazan, owned by private enterprise.
  • The second power plant in the country built by a private enterprise.
  • One of the fastest project that became operational after the decision phase.
  • The most efficient engine type natural gas-powered power plant in the country