10.05.2023 - Consolidated EBITDA as of 31.03.2023

The planned maintentance and necessary revisions of Çan2 Thermal Power Plant (Operating within the Group's Subsidiary of Çan2 Termik A.Ş.) were carried out in between 02 March 2023 – 08 April 2023 for the fiscal year of 2023 (the last of which was in October 2021).

  

Considering the such planned maintenance and necessary revisions, as the Power Plant did not operate between these dates, the consolidated EBITDA level of Odaş Group was realized TRY 373 Mn in the period of 01.01.2023 – 31.03.2023.

 

In contradiction between the Turkish and English versions of this public disclosure, the Turkish version shall prevail.